Britain's Railway Didn't Fail Because It Was Private. It Failed Because It Was Split.

For thirty years Britain ran one railway as dozens of businesses trading through contracts. The cost of those contracts is what Great British Railways is really being built to remove. Britain's railway, Part 3 of 4.

Britain's Railway Didn't Fail Because It Was Private. It Failed Because It Was Split.

Tags: Railways, Infrastructure, Innovation, Great British Railways

Britain's Railway Didn't Fail Because It Was Private. It Failed Because It Was Split. | The Infinite Loop
The Infinite Loop Ideas for a Better World

Britain's railway, Part 3 of 4

Britain's Railway Didn't Fail Because It Was Private. It Failed Because It Was Split.

For thirty years Britain ran one railway as dozens of businesses trading with each other through contracts. The cost of those contracts, more than any profit, is what Great British Railways is really being built to remove.

Somewhere in Britain today, a train will run late, and two organisations will pay people to argue about whose fault it was. When the government set out its plan for rail reform in 2021, it put a number on this. The railway employed "almost 400 full-time staff, known as 'train delay attributors', to argue with each other about whose fault a delay is." Around 40% of delays, it said, were disputed. (Plan for Rail, 2021)

How one late train becomes an argument

Because track and train are separate businesses, every delay has to be pinned on one of them before anyone gets paid.

TRACK OWNERNetwork Rail TRAIN OPERATORa separate company LATE "The train's fault" "The track's fault" DISPUTED £
400

Almost 400 people worked full time as "train delay attributors": their job was to argue with the other side about whose fault each delay was.

So what? None of that work gets the next train there on time. It decides which side of a contract pays. It exists because track and train were set up as separate businesses.

An illustrative delay. Figures from the government's 2021 Plan for Rail.

Sources HIGH
Williams-Shapps Plan for Rail (2021), p.15: "almost 400 full-time staff, known as 'train delay attributors'"; "Around 40% of delays are disputed". Network Rail, Payments for disruption: payments reflect who caused the delay.

Those 400 people are not a scandal. They are a symptom of how the railway was rebuilt in the 1990s: the company that owns the track and the companies that run the trains became separate businesses, paid by contract and compensated by formula.

Part 1 of this series argued that the ownership debate is mostly settled. Part 2 asked what happens when the new integrated railway decides who may compete with it. This part asks the question underneath both: what did splitting the railway actually cost, and does putting it back together fix it?

Predicted in 1994

None of this was a surprise. In July 1994, as British Rail was being broken up, economists at the University of Leeds Institute for Transport Studies set out what the new structure would create: 25 train operating companies, at least six freight and parcels businesses, and a single infrastructure owner, Railtrack. Among the problems they expected from separating track from train was, in their words, "an increase in transaction costs between Railtrack and train operators". (Shires et al., 1994)

One railway becomes a web of contracts

The structure the Leeds economists described in 1994: every operator tied to the track owner by contract.

RAILTRACKBritish Rail
Railtrack, owner of the track25 train operating companiesAt least 6 freight and parcels businessesContracts
Sources HIGH

Transaction costs are the price of doing business across a boundary: finding the other party, writing the contract, monitoring it, and arguing when it goes wrong. Inside a single organisation, a manager settles those questions. Between two organisations, a contract has to. The privatised railway turned thousands of everyday operational decisions into contractual ones.

The day the interface failed

At 12.23pm on 17 October 2000, a GNER express from King's Cross to Leeds was rounding a bend between Welham Green and Hatfield at 115mph when the rail beneath it shattered. Four people died and more than 100 were injured. The rail had failed through gauge corner cracking, a form of metal fatigue caused by the repeated pressure of wheels on the rail. (Hansard; [2006] EWCA Crim 1586)

The cracking was not a secret. Railtrack, which owned the track, had contracted its inspection and maintenance to Balfour Beatty under a seven-year, £368 million contract. When the companies were prosecuted, the Court of Appeal set out what had happened. It had been decided that this section of rail needed replacing. "There was then a delay of 9 months, in the course of which new rail was delivered, but left to lie beside the track." The rail was not replaced before the derailment.

The trial judge called Balfour Beatty's failure "the worst example of sustained, industrial negligence in a high-risk industry I have seen", and Railtrack's failure to ensure the rail was replaced "incompetence of a serious order". Balfour Beatty was fined £10 million, reduced on appeal to £7.5 million. Railtrack was fined £3.5 million.

The organisation that owned the track did not maintain it, and the organisation that maintained it did not own it.

The replacement rail lay beside the line, in the gap between them.

The consequences ran far beyond one crash. Railtrack was placed in railway administration on 7 October 2001. Its business was taken over a year later by Network Rail, a company limited by guarantee with no shareholders. The National Audit Office later reported that Network Rail's spending was forecast to remain 30% higher than before Hatfield by the end of the 2008-09 settlement. (NAO, 2004)

Thirty years of splitting and stitching

From the warning to the remedy.

1994
Leeds economists warn of higher transaction costs between track and train
2000
Hatfield: four people die after a cracked rail shatters
2001
Railtrack placed in railway administration
2002
Network Rail takes over, with no shareholders
2011
McNulty finds a 40% efficiency gap and calls for track and train to be realigned
2021
Plan for Rail: track and train to come together in a "guiding mind"
Next
GBR operational around 12 months after Royal Assent
Sources HIGH
Shires et al. (1994); Hansard (2000); NAO (2004); Realising the Potential of GB Rail (2011); Plan for Rail (2021); GOV.UK, Great British Railways, updated 20 September 2026.

The bill for being split

A decade later, the Department for Transport and the rail regulator commissioned a study, led by Sir Roy McNulty, into why Britain's railway cost so much. His May 2011 report found "an efficiency gap of 40% against four European comparators". There were many reasons, and McNulty did not blame them all on structure. But structure was central to his diagnosis. The incentives on Network Rail and the train operators, he wrote, were "almost completely different". Operators were insulated from changes in track access charges, so "they have no incentive to minimise NR's costs." (McNulty, 2011)

His remedy was to begin reconnecting track and train: joint ventures and alliances between Network Rail routes and operators, and at least one vertically integrated pilot.

Busy railways pay more for the split

Is splitting track from train always costly? The international evidence says it depends on how busy the railway is.

Fumitoshi Mizutani and Shuji Uranishi studied 30 railway organisations in 23 European and East Asian countries between 1994 and 2007. They found that separating infrastructure from operations tends to reduce costs where train density is low, and to increase them where density is high. (Mizutani and Uranishi, 2013) The intuition is straightforward, even if the paper's job is to measure rather than explain it. On a quiet network there is spare capacity and little for track and train to coordinate. On a crowded one, every train affects every other, and each of those interactions has to be managed across the boundary.

Splitting helps quiet railways and hurts busy ones

And Britain runs one of the busiest passenger networks in Europe.

BUSY NETWORKS TRAIN DENSITY → COST SEPARATED INTEGRATED UK

Most intensive passenger networks, IRG-Rail countries

  1. 1Netherlands
  2. 2Switzerland
  3. 3Denmark
  4. 4United Kingdom

The chart illustrates the direction of the finding; it does not plot the paper's estimates. The ranking is for passenger service intensity, 2022 data.

Sources HIGH

Britain's network is crowded. Among the countries monitored by the Independent Regulators' Group for rail, the intensity of passenger services on the network was highest in the Netherlands, followed by Switzerland, Denmark and the UK. Britain applied a structure suited to quiet networks to one of the busiest in Europe.

The country that privatised and kept it whole

Japan offers the clearest contrast, because it privatised too. On 1 April 1987, Japanese National Railways, carrying liabilities of ¥37.1 trillion, was divided into six regional passenger companies and a freight company. The crucial difference was where the lines were drawn. Japan divided its railway by geography, not by function. Each passenger company took over the railway in its region, track and trains together. The freight company, which owns almost no lines of its own, pays track access charges to them. (JR East Annual Report)

Split by function, or by geography

Both countries privatised. Only one put a contract between the track and the train.

Britain from 1994

Split by function

Every delay crosses a contract. Money follows the blame.

Japan from 1987

Split by geography

Each company owns its track and runs its trains. Freight pays the regional companies for access.

Schematic, not a map.

Sources HIGH

JR East became a fully private company in June 2002. Central Japan Railway, which runs the Tokaido Shinkansen between Tokyo and Osaka, "owns and is responsible for maintaining all systems necessary for operation", from rolling stock and track to signals and power. It reports 372 departures a day on the line and an average delay of 1.6 minutes per train. (JR Central Data Book 2025)

Departures per day
372
Average delay per train
1.6MIN
TOKAIDO SHINKANSEN · TOKYO TO OSAKA · AS REPORTED BY JR CENTRAL, DATA BOOK 2025
Sources HIGH
JR Central Data Book 2025, p.6. JR Central does not state the measurement basis or year in this source, so the figure is not compared with British punctuality.

Japan is not a template. Its geography, its cities and its history are different, and its railways do many things Britain's do not. But it settles one argument.

Ownership and integration are separate questions. Britain spent thirty years debating the first while living with the consequences of the second.

What Great British Railways changes

The 2021 Plan for Rail named the problem directly. "Track and train will come together in a 'guiding mind' for the system, Great British Railways," it said, and "the cottage industry of costly commercial disputes over delay attribution will end."

That is now under way. The government expects GBR to be operational around 12 months after the Railways Bill receives Royal Assent. Integrated track and train leadership teams already run the Anglia, South Eastern and South Western regions, with more to follow. (GOV.UK)

This is the reform's strongest argument, and it explains why the government has been willing to accept the trade-off described in Part 2. Integration removes the boundary that generated the contracts, the compensation regimes and the 400 attributors. It also puts the organisation that now runs both sides of that boundary in charge of deciding who else gets to use it. Both things are true at once. The task for the Lords, and later for GBR's board, is to keep the first benefit without paying too much for the second.

What this means for leaders

The railway is an unusually visible example of something most organisations live with quietly. Wherever the people who own an asset are separated from the people who serve the customer, an interface appears, and interfaces generate cost: service agreements, internal recharges, escalation procedures, and people whose job is to decide whose problem something is.

Some of those interfaces are worth their cost, because they create focus, competition or accountability that would otherwise be missing. Many are not. A useful test is the railway's own: how many of your people are paid to argue about whose fault something is? If the answer is more than a handful, the problem may not be the people on either side. It may be where you drew the line between them.

Your turn: the railway's test

How many of your people spend much of their time deciding whose fault, or whose problem, something is?

Pick oneThe answer says more about where your boundaries sit than about the people on either side of them.

If the answer is more than a handful, look first at where the line between teams is drawn, not at the people on either side of it.

Thanks for reading,
Ideas for a Better World Editor, Simon Hill

About the Editor: Founder of Wazoku including Innocentive, author of the award winning Expected Value, Mapping Value, TEDx speaker and innovation thought leader.

How we checked this piece

Every factual claim in this article is graded HIGH against a named primary source. Interpretation is presented as such.

ClaimGradeSource
"almost 400 full-time staff… train delay attributors"; around 40% of delays disputed; "guiding mind"; "cottage industry… will end"HIGH, verbatimPlan for Rail (2021), pp.15, 23, 31
July 1994; 25 train operating companies; at least six freight and parcels companies; "an increase in transaction costs between Railtrack and train operators"HIGH, verbatimShires, Preston, Nash and Wardman, ITS WP 419
Hatfield, 12.23pm on 17 October 2000; King's Cross to LeedsHIGHHansard, Lords, 19 October 2000
115mph between Welham Green and Hatfield; 4 deaths, over 100 injured; gauge corner cracking from rolling contact fatigue; £368m seven-year contract; 9-month delay with new rail "left to lie beside the track"; judge's words; fines £10m (reduced to £7.5m) and £3.5mHIGH, verbatimR v Balfour Beatty Rail Infrastructure Services Ltd [2006] EWCA Crim 1586
Railtrack into administration 7 October 2001; Network Rail from October 2002, no shareholders; spending 30% above pre-Hatfield by 2008-09HIGH, verbatimNAO (2004), paras 2, 3, 6
McNulty: DfT and ORR commissioned; May 2011; "efficiency gap of 40%"; "almost completely different"; "no incentive to minimise NR's costs"; alliances and integrated pilotHIGH, verbatimRealising the Potential of GB Rail
30 organisations, 23 countries, 1994 to 2007; separation cuts cost at low density, raises it at high densityHIGHMizutani and Uranishi (2013)
Passenger intensity highest in Netherlands, Switzerland, Denmark, UKHIGHIRG-Rail 12th report, p.8
1 April 1987; ¥37.1tn liabilities; six passenger companies and one freight; freight pays access charges; JR East fully private June 2002HIGHJR East AR 2005; AR 2006
JR Central owns and maintains all systems; 372 daily departures; 1.6-minute average delayHIGHJR Central Data Book 2025, pp.6, 8
GBR operational around 12 months after Royal Assent; integrated leadership in Anglia, South Eastern, South WesternHIGHGOV.UK, updated 20 September 2026